File #: 2016-420    Version: 1 Name:
Type: Staff Report Status: Passed
File created: 10/3/2016 In control: City Council
On agenda: 10/12/2016 Final action: 10/12/2016
Title: Amendments to the Cooperative Agreement with CVAG for the Whitewater Bike Path
Attachments: 1. CVAG Cooperative Agreement - Cathedral City Whitewater Channel Bike Path Construction
City Council

MEETING DATE: 10/12/2016
TITLE:
Title
Amendments to the Cooperative Agreement with CVAG for the Whitewater Bike Path
End

FROM:
John A. Corella, P.E. - City Engineer

RECOMMENDATION:
Recommendation
Staff recommends the City Council approve amendments to the Cooperative Agreement with CVAG for the Cathedral City Whitewater Bike Path to allow the use of South Coast Air Quality Management District CV Link Grant Funds for construction of the project.
Body


BACKGROUND:
On November 16, 2015, Council approved an Intergovernmental Agreement with the Coachella Valley Association of Governments (CVAG) to complete the Cathedral City Bike Path, which is planned on the west bank of the Whitewater River Channel between Vista Chino Drive and Ramon Road. Cathedral City hired the same design and environmental consulting firms that were working on CV Link so that the Cathedral City Bike Path would be designed consistent with CV Link standards. The City paid for the design and environmental work with Caltrans Bicycle Transportation Account (BTA) grant funds. On July 13, 2016, the Cathedral City Council certified the Bike Path Initial Study/Mitigated Negative Declaration Addendum, in compliance with California Environmental Quality Act (CEQA).

DISCUSSION:
The City of Cathedral City received six bids for the project, which were opened on August 30, 2016. The lowest bid, from CT&T Concrete Paving, was for $3,165,171.74. The City has $450,000 budgeted for construction of the Bike Path, primarily from a Bicycle Transportation Account (BTA) grant from Caltrans. The South Coast Air Quality Management District (SCAQMD) awarded CVAG $17,400,000 in Sentinel Mitigation (AB 1318) funds for construction of the CV Link project. CVAG's agreement with SCAQMD identifies funding for an "early action segment". CVAG proposes to allocate the designated early action segment funds and, as necessary, other SCAQMD funds, for construction of the Cathedral City Bike Path. ...

Click here for full text