File #: 2016-569    Version: 1 Name:
Type: Staff Report Status: Passed
File created: 1/3/2017 In control: City Council
On agenda: 3/8/2017 Final action: 3/8/2017
Title: Authorization for Roof Replacement on the Public Works Building and Adjacent Maintenance Utility Building

City Council

 

MEETING DATE: 3/8/2017                                                                                                                              

TITLE:

Title

Authorization for Roof Replacement on the Public Works Building and Adjacent Maintenance Utility Building                     

End

 

FROM:                                          

Tami E. Scott, Administrative Services Director

 

RECOMMENDATION:                     

Recommendation                     

Staff recommends the City Council authorize a complete reroofing of the Public Works Building and the adjacent Maintenance Utility Building located at 68385 Kieley Rd for an amount not to exceed $54,144.

Body

 

 

BACKGROUND:

The Public Works Building, located on 68385 Kieley Rd., was built in 1987.  Since that time it has only had roof patching and repairs.  Due to the condition and age of the roof and a multitude of leaks that can no longer be addressed through repairs, the entire roof needs to be replaced.  In addition, the adjacent maintenance utility building is also in the same condition. 

 

 

DISCUSSION:

Due to the condition of the roof, staff proceeded with a bid process for complete roof replacements. Staff received three bids and recommends accepting the most qualified and the lowest bid from Castro Roofing of Thousand Palms in an amount not to exceed $35,783 for the Public Works Building and $7,241 for the adjacent maintenance utility building.  The roofing system will be one (1) layer of 1/2" EPS insulation then a Carlisle 60 mil TPO (Thermoplastic PolyOlefin) heat welded roof system.  In addition, there will be $6500 of air conditioning removal and refitting and $4,620 to replace 10 plastic drains with copper drains.

 

 

FISCAL IMPACT:

Funding is available in 614 Facilities Fund in the FY16-17 budget in the amount of $54,144.

 

 

ATTACHMENTS:

None