TITLE:

Title

Intergovernmental Memorandum of Understanding with the Agua Caliente Band of Cahuilla Indians regarding the Ramon Road Bridge Widening and Vista Chino Resurfacing Improvements.

End

 

FROM:                                          

John A. Corella, P.E., City Engineer

 

RECOMMENDATION:                     

Recommendation                     

Staff recommends the City Council authorize the Mayor to Execute the attached Intergovernmental Memorandum of Understanding (MOU) with the Agua Caliente Band of Cahuilla Indians (ACBCI) regarding Tribal Transportation Program Funding for the Ramon Road Bridge Widening and Vista Chino Resurfacing Improvements.

Body

 

BACKGROUND:

There are two projects involved in the MOU.  The first is the Ramon Road Bridge over the Whitewater River.  The purpose of this bridge project is to eliminate the roadway lane constriction across the existing Whitewater River Bridge and westerly to San Luis Rey Drive.  The City of Palm Springs and Cathedral City share a common jurisdictional boundary along the centerline of Ramon Road between San Luis Rey Drive and Landau Boulevard.  The City of Palm Springs is the designated lead agency for this project.  This bridge project is currently under design and environmental clearance review.   

The second project listed in the MOU is the Vista Chino Resurfacing Improvements.  Vista Chino has been identified as needing raised median curbs and new pavement.  This Project is currently identified under two projects within the current five-year Capital Improvement Plan (CIP).  One project from Date Palm Drive to Landau Boulevard (East) and the other project from Landau Boulevard to the west City Limits at the Whitewater River (West).

 

Under this MOU, ACBCI will provide up to $2.15 million toward the construction of the three projects. Staff has estimated that approximately $0.5 million will be required for each of the Vista Chino projects and $1.15 million for the Ramon Road Bridge Widening project.

 

DISCUSSION:

Both of the projects will require NEPA and CEQA environmental clearances. The Ramon Road clearances are in process and the Vista Chino Resurfacing Improvements will obtain the required clearances during the design phase.

 

 

FISCAL IMPACT:

The funding from ACBCI will be used to supplement the funding included in the current five-year CIP for the Vista Chino and Ramon Road projects.  City Staff will provide the City Council with the final funding details for each of the projects as each nears the construction phase.

 

ATTACHMENTS:

Intergovernmental Memorandum of Understanding