Legislation Details

File #: 2016-99    Version: 1 Name:
Type: Staff Report Status: Passed
File created: 3/7/2016 In control: City Council
On agenda: 10/12/2016 Final action: 3/23/2016
Title: Approve the Right of Way Phase of the Cathedral Canyon Bridge and the Date Palm Bridge Projects
Attachments: 1. Cathedral Canyon Drive Bridge Project Right 0f Way Summary Report, 2. Date PalmDrive Bridge Project Right of Way Summary Report
City Council

MEETING DATE: 3/23/2016
TITLE:
Title
Approve the Right of Way Phase of the Cathedral Canyon Bridge and the Date Palm Bridge Projects
End

FROM:
John A. Corella, P.E. - City Engineer

RECOMMENDATION:
Recommendation
Staff recommends the City Council approve the Right of Way phase of the Cathedral Canyon Bridge Project (CIP No. 8919), and the Date Palm Bridge Project (CIP No. 8914) and accept the easements and other conveyances necessary to construct each bridge project; and authorize the City Manager to execute the easement and utility agreements and all ancillary documents necessary for each bridge project; and authorize the payments for the easements and other costs associated with the Right of Way portion for each bridge project.
Body


BACKGROUND:
Caltrans requires Right of Way (R/W) Certification for any project for which Plans, Specifications, and Estimates (PS&E) are submitted to the district/region or Headquarters. R/W Certification is a written statement summarizing the status of all right of way related matters pertaining to a proposed construction project. The purpose of the R/W Certification is to confirm that the project to be constructed is ready for advertising and affirms the following:
? Real property interests have been, or are being, secured; and
? Physical obstructions including utilities and railroads have been or will be removed, relocated, or protected as required for construction, operation, and maintenance of the proposed project; and
? Right of way acquisition and relocation assistance program requirements have been conducted in accordance with applicable federal and state laws and procedures.


DISCUSSION:
For the Cathedral Canyon Drive Bridge Project and the Date Palm Drive Bridge Project ("Projects," collectively) compliance with Caltrans R/W standards and requirements include the acquisition of permanent easements and temporary construction easements. The City is obligated to compensate the proper...

Click here for full text